The one number most small remodelers don't track: over/under billing
I'm the controller at a remodeling company. The thing I see trip up small contractors more than anything isn't bad estimating. It's not knowing whether you've billed ahead of the work or behind it.
Quick version:
- Take actual cost to date divided by projected final cost. That's your % complete.
- Multiply that by your contract (including approved change orders). That's what you've actually earned.
- Subtract that from what you've invoiced.
Positive = you're overbilled. Good for cash, but that money isn't profit yet.
Negative = you're underbilled. You're financing the job for your client.
If you're running 3 jobs that are all underbilled, that's usually why the bank account feels tight even when the jobs look profitable on paper.
The other one is profit fade: what the estimate said you'd make vs. what you're projected to make now. Checking it weekly catches a bleeding job while you can still fix it.
Happy to answer questions.